FCC conditionally clears up to 1 million SpaceX satellites for orbital AI data centers
Edited and reviewed by AI Ping Editorial Team
Key points
- Deployment above 600 kilometers requires a final orbital debris plan.
- SpaceX plans to route data through optical links and Starlink to reach ground stations.
- The first satellite is due in operation by November 25, 2033, and the full constellation by November 25, 2040.
The US Federal Communications Commission’s Space Bureau on November 25 conditionally authorized Starmind, a proposed SpaceX network of up to one million satellites that would perform AI computing in orbit for use on Earth. The first deadline is November 25, 2033, when at least one satellite must be operating in its assigned orbit.
SpaceX’s January application proposed altitudes from 500 to 2,000 kilometers. The grant lists 500 to 1,002 kilometers. The bureau accepted the debris plan below 600 kilometers. Before deploying satellites that will operate above 600 kilometers, SpaceX must file a license modification with its final debris plan, including disposal.
The FCC’s disposal rule starts the clock at the end of a mission. For a spacecraft passing through low Earth orbit and slated for uncontrolled atmospheric reentry, disposal must take place as soon as practicable and within five years. Time spent in orbit after retirement leaves more opportunity for a collision that creates debris. For a satellite equipped to maneuver, the FCC counts the mission as over when the spacecraft can no longer take action to avoid a collision. The bureau deferred SpaceX’s request to use disposal orbits around Earth or the Sun for higher satellites.
How computing traffic would reach the ground
In its January 30 application, SpaceX described how data would get back to Earth. Optical links would carry traffic between computing satellites and could connect them to first- and second-generation Starlink satellites. Starlink’s laser network would then relay traffic to authorized ground stations. SpaceX identified electricity supply as a reason to put computers in orbit. It proposes powering the equipment with sunlight collected at the spacecraft, reducing its reliance on terrestrial electricity grids.
The grant covers backup radio communications with the ground. If the optical network fails, controllers can receive information about a satellite’s condition, track it and send commands by radio. That gives them a way to reach a spacecraft when its normal link is down.
Reflected sunlight and waste heat
The American Astronomical Society warned that a satellite reflecting sunlight can leave a streak across an exposure. Sunlight scattered by the atmosphere from many spacecraft could also brighten the background sky, making it harder to distinguish a faint object even away from a streak. In its March response, SpaceX described testing ways to shade parts of the spacecraft or change the orientation of solar arrays. It is refining models to predict how bright a satellite would look from different directions on the ground.
The society also raised a concern about infrared telescopes. Their instruments can pick up waste heat from computers in orbit. Across a large constellation, those emissions could raise the infrared background against which astronomers measure their targets. SpaceX said it would work with the National Science Foundation to characterize emissions at relevant wavelengths and develop infrared guidelines.
The bureau accepted that commitment and declined to add optical astronomy conditions. It considered waste heat beyond the scope of its radio authorization.
When the satellites must be operating
Once the first satellite is operating in its assigned orbit, it starts a 90-day clock. Under the new FCC rules, a licensee meets the initial milestone by notifying the agency that at least one spacecraft has operated under the terms of its license for that entire period. The staged test gives operators time to develop their spacecraft while discouraging them from holding spectrum rights without putting satellites to work.
For Starmind, the next deadline is November 25, 2035, when 10 percent of the authorized maximum, or 100,000 satellites, must be operating in their assigned orbits. The halfway point, 500,000 satellites, is due on the same date in 2038. The remaining satellites must be in place and operating by November 25, 2040. Within 15 days of each deadline, an operator must demonstrate compliance or notify the FCC in writing that it missed the milestone.
Sources
- Starmind authorization and grant conditions (DA 26-1273) — FCC Space Bureau
- FCC authorizes orbital data-center satellites (Nov. 25) — Federal Communications Commission
- Public notice on the SpaceX orbital data-center application (DA 26-113) — FCC Space Bureau
- Orbital Data Center System — response to petitions (March 16) — SpaceX
- Petition concerning the orbital data-center application — American Astronomical Society
- Post-mission disposal in low Earth orbit (FCC 22-74) — Federal Communications Commission
- Guidance on the transition to new deployment milestones (DA 26-1080) — FCC Space Bureau
- Space Modernization order — deployment milestones (FCC 26-47) — Federal Communications Commission