L&T wins order for more NVIDIA B300 GPUs at its Chennai cluster
Edited and reviewed by AI Ping Editorial Team
Key points
- The planned 10,000 GPUs cover the whole cluster.
- The new contract falls in the 25 billion to 50 billion rupee band.
- L&T previously set January 2027 as the target for commissioning.
Larsen & Toubro disclosed a multi-year order on November 23 for its subsidiary LTN Compute to deploy additional NVIDIA B300 GPUs in Chennai for an inference infrastructure provider.
The 10,000 GPUs in the Chennai project date to the original plan L&T announced on August 13 with US cloud company Together AI. That figure describes the capacity of the cluster. This allocation is part of that cluster. Its size and the customer's name remain undisclosed.
Two orders, a separate investment estimate
The November order falls in L&T’s large category, covering 2,500–5,000 crore rupees. One crore is ten million, which puts the endpoints at 25 billion and 50 billion rupees. The August deal fell into the company's mega category, covering 10,000 crore to 15,000 crore rupees. Each band spans a range of possible contract values. The upper endpoint alone conveys no agreement on a price.
On October 27, an analyst asked management how much capital L&T expected to put into the Chennai GPUs. Management estimated the investment associated with the 10,000 processors at about $750 million. That estimate concerns the money the operator expects to invest. The order bands describe business coming in from customers over the life of their contracts.
What is due in January 2027
On that call L&T said Together AI had taken a significant share of capacity under a long-term agreement. Management was targeting January 2027 to commission the AI factory. Commissioning is a milestone for the facility as a whole. An enterprise planning a deployment would still need a date for access to its own allocation. Together AI, the partner in the August deal, says its own operating process includes testing each GPU before admitting it to a cluster and monitoring hardware health in service.
Physical expansion is under way at the campus. On October 28, Vyoma.AI announced it had broken ground on a 52-megawatt data center. It described an existing 30 MW facility on the site as operational. The new building is designed to remove heat from densely packed equipment using direct-to-chip liquid cooling. The operator lists the existing facility as MAA 01. It offers space for customers' own equipment, redundant power and uninterruptible power supplies, and a choice of network carriers.
The operator describes 250 MW as feasible power provision for the campus, the same figure L&T gives for its first-phase design. Vyoma has separately reported 150 megavolt-amperes of electrical infrastructure ready at the site. Megawatts measure real power. Megavolt-amperes measure apparent power, and converting between the two requires a power factor. Dividing 150 by 250 would give no measure of construction progress.
The AI factory design couples the processors with high-speed networking and parallel storage. Servers working together on a model need to move data between chips and read and write it across the cluster. The distinction between chips and servers matters for a project of this size. NVIDIA's own DGX B300 system, for example, houses eight Blackwell Ultra GPUs. Working out a server count for Chennai would require knowing which configuration LTN Compute will install.
The customer plans to train, fine-tune and serve specialist models commercially. Inference uses a trained model to generate a result from a new input. A service therefore consumes computing capacity as customers submit requests, after the training run has ended.
L&T is organizing colocation under Vyoma and AI computing under LTN Compute. Vyoma also markets GPU capacity to enterprises through several service formats. Customers can run workloads on virtual machines, use serverless GPUs that scale with demand, or take dedicated bare-metal servers with control of the hardware. For businesses considering the new Chennai capacity, the applicable booking terms and hourly rates remain open.
Sources
- Chennai AI cluster order filing — Larsen & Toubro / NSE
- August partnership and earlier order with Together AI — Larsen & Toubro
- October 27 earnings call and investor questions — Larsen & Toubro Investor Relations
- October 28 groundbreaking for the 52 MW Chennai facility — Larsen & Toubro
- Chennai data center and MAA 01 facility — Larsen & Toubro–Vyoma
- DGX B300 system specifications — NVIDIA
- Watts, volt-amperes and power factor — Schneider Electric
- Deep learning training and inference — NVIDIA
- AI Factory and GPU service formats — Larsen & Toubro–Vyoma
- Frontier AI Factory operating model — Together AI